New York City casino projects face tax, planning and financing hurdles
Business4 min read
Summary
Three casino projects awarded New York City licences nearly a year ago face different challenges as development continues. Resorts World reportedly faces an $80.6m state bill over horse-racing support payments, Hard Rock Metropolitan Park is awaiting city design approval, and Bally’s has secured initial construction financing.
New York City’s casino license winners are encountering new challenges as they work on their projects, nearly a year after receiving their licenses.
New York State Gaming Commission financial reports put Resorts World's outstanding state payments at $80.6m through October. The amount in dispute could exceed $180m by June 2027. All three licensees agreed to support horse racing, but Resorts World must cover the payments until the other casinos are planned to open in 2030, leaving it liable for nearly $500m until then.
Resorts World wants the payments deducted from its overall taxes, whereas the state treats them as an additional obligation. Its winning bid committed it to tax rates of 56% on slot revenue and 30% on table game revenue. Resorts World contends that paying the racing support on top of gaming taxes would bring its effective slot tax rate to approximately 72%. Under an October interim agreement, Resorts World can send racing support payments directly to the New York Racing Association during negotiations. The state nevertheless continues to claim the unpaid tax revenue. The added financial burden could threaten the planned expansion, Resorts World executives have previously suggested, according to New York Focus.
Resorts World relies on operating cash flow to fund later stages of its $5.5bn development and began work on its second phase in July. The phase includes a 400-room hotel tower, a 7,000-seat entertainment venue, a central plaza and a car park. The casino began commercial operations on 28 April with 2,500 slots and 242 table games, adding another 1,400 slots in July and a high-limit gaming area in October.
Gaming Commission data showed Resorts World generated $794.3m in gross gaming revenue through October, with monthly revenue between $122m and $136m since May, its first full month of commercial operations. From May to October, the average daily number of slots and electronic table games rose 61% to 4,024, but their revenue fell 9.5% as average daily win per machine declined from $1,275 to $716. Monthly table game revenue doubled since introduction and rose 54% since mid-May, partly offsetting the decline. Through 15 November, the casino had generated $859.6m since its commercial launch and had 4,137 slots and electronic table games and 345 table games. Resorts World projected $2.2bn in gross gaming revenue by 2027 in its application.
Community opposition persists at the $8.1bn Metropolitan Park development, which is backed by New York Mets owner Steve Cohen and Hard Rock International. New York City's Public Design Commission deferred a design vote on Monday because a five-hour meeting left insufficient time for all public testimony; it was the second postponement in just over a month. The commission had voted unanimously to table the proposal on 20 October, seeking more detail on stormwater mitigation and revisions to façades, pedestrian circulation and public access. Developers have since amended the plans, including the stormwater measures. The commission oversees building design rather than the casino licence, but its decision could significantly delay construction.
Metropolitan Park was about five and a half months behind the schedule it gave state regulators, the Queens Daily Eagle reported in May. The developers’ targets for starting foundation testing in January and casino construction in April had slipped, despite progress on preparatory work. Metropolitan Park said at the time that its planned 2030 opening would remain on track. The GFLB had earlier questioned whether the opening schedule was realistic, citing the development’s scale and the constraints of building in an urban setting.
Financing led by WhiteHawk Capital Partners will cover pre-construction and certain development expenses for Bally’s Bronx, the company said on 2 October when it announced the $400m deal. Bally’s confirmed in its third-quarter filings that an additional $160m was available for future draws. The high-interest loans mature in April 2028, over two years before the planned opening of the $4bn development. During licensing, the GFLB raised concerns about Bally’s finances, including whether its guarantee to finish the project and meet financial obligations was sufficiently strong.
Bally’s warned in its recent third-quarter earnings of potential difficulty meeting debt obligations, its second consecutive quarterly warning. The company also disclosed that it had fallen short of a minimum liquidity requirement at the end of September. It later announced $560m in additional financing commitments intended to improve liquidity. The development site cost $157m when the company bought it in February; construction permit applications followed in July. The PDC gave preliminary approval to reconstruct Ferry Point Park's northeastern section in October and its western section in November. Bally’s planned to start construction in 2027, while both new-build casinos continue to target openings in 2030.
The Gaming Facility Location Board's consultants projected that the three casinos could produce $5.5bn in annual gross gaming revenue by 2033 and approximately $7bn in incremental gaming tax revenue between 2027 and 2036. The board also raised concerns about financing, revenue forecasts and ambitious construction schedules. Metropolitan Park's bid is scheduled to return to the PDC on 30 November.